ADP No. 833 LTBC
Up gradation of Maternity home into 50 bedded hospital at Kamal Khan Goth
- ADP No.
- 833
- District(s)
- Malir
- Division
- Karachi
- Facility type
- Hospital / institute / other facility
- ADP target date
- 30-06-2027
- LTBC
- Yes
- Executing agency
- Works & Services Department (capital); Procurement, Monitoring & Implementation Cell, Health Department (revenue)
Capital as on 23-10-2026 · Revenue as on 23-10-2026. Rs in million.
Up to 30 June 2026
Approved cost558Latest approved cost
Utilized to 30 June 202646883.9% of cost · ADP estimate
Throw-forward90Balance as on 1 July 2026 · equal to allocation for 2026-27
Financial year 2026-27
Allocation90Capital90.000RevenueNil
Released32Capital31.500RevenueNil
Utilized30Capital29.728RevenueNil
By component Utilization against funds released
Capital
94.4% of release utilizedAllocation90.000Released31.500Utilized29.728Of allocation33.0%Revenue
AllocationNilReleasedNilUtilizedNilReleased and utilized against allocation, 2026-27
Photographs


How to read this page
Approved cost is the latest approved cost of the scheme. Utilized to 30 June 2026 is the estimate printed in the ADP. Throw-forward is the balance of the approved cost on 1 July 2026.
Allocation is the amount provided in the ADP 2026-27. Released is the amount released so far this year. Utilized is the amount utilized out of the funds released. Capital and revenue are shown separately and are never added into one percentage.
LTBC means the scheme is likely to be completed by June 2027. All amounts are in Rs million.