Health ADP 2026-27Health Department · Government of SindhScheme dashboard — sign in

ADP No. 881  LTBC

Up gradation of BHU to RHC Akil, Taluka Larkana

ADP No.
881
District(s)
Larkana
Division
Larkana
Facility type
RHC
ADP target date
30-06-2027
LTBC
Yes
Executing agency
Works & Services Department (capital); Procurement, Monitoring & Implementation Cell, Health Department (revenue)

Capital as on 23-10-2026 · Revenue as on 23-10-2026. Rs in million.

Up to 30 June 2026

Approved cost178Latest approved cost
Utilized to 30 June 20267742.9% of cost · ADP estimate
Throw-forward102Balance as on 1 July 2026 · equal to allocation for 2026-27

Financial year 2026-27

Allocation102Capital66.558Revenue35.161
Released58Capital23.296Revenue35.161
Utilized9.984Capital9.984RevenueNil

By component Utilization against funds released

Capital

42.9% of release utilizedAllocation66.558Released23.296Utilized9.984Of allocation15.0%

Revenue

0.0% of release utilizedAllocation35.161Released35.161UtilizedNilOf allocation0.0%

Released and utilized against allocation, 2026-27

Capital

  • Allocation66.558
  • Released23.296
  • Utilized9.984

Revenue

  • Allocation35.161
  • Released35.161
  • UtilizedNil

How to read this page

Approved cost is the latest approved cost of the scheme. Utilized to 30 June 2026 is the estimate printed in the ADP. Throw-forward is the balance of the approved cost on 1 July 2026.

Allocation is the amount provided in the ADP 2026-27. Released is the amount released so far this year. Utilized is the amount utilized out of the funds released. Capital and revenue are shown separately and are never added into one percentage.

LTBC means the scheme is likely to be completed by June 2027. All amounts are in Rs million.