ADP No. 885 LTBC
Construction of BHU at Kandhra colony Moro
- ADP No.
- 885
- District(s)
- Naushahro Feroze
- Division
- Shaheed Benazirabad
- Facility type
- BHU
- ADP target date
- 30-06-2027
- LTBC
- Yes
- Executing agency
- Works & Services Department (capital); Procurement, Monitoring & Implementation Cell, Health Department (revenue)
Capital as on 23-10-2026 · Revenue as on 23-10-2026. Rs in million.
Up to 30 June 2026
Approved cost40Latest approved cost
Utilized to 30 June 202640100.0% of cost · ADP estimate
Throw-forward0.001Balance as on 1 July 2026 · equal to allocation for 2026-27
Financial year 2026-27
Allocation0.001Capital0.001RevenueNil
ReleasedNilCapitalNilRevenueNil
UtilizedNilCapitalNilRevenueNil
By component Utilization against funds released
Capital
Allocation0.001ReleasedNilUtilizedNilRevenue
AllocationNilReleasedNilUtilizedNilReleased and utilized against allocation, 2026-27
How to read this page
Approved cost is the latest approved cost of the scheme. Utilized to 30 June 2026 is the estimate printed in the ADP. Throw-forward is the balance of the approved cost on 1 July 2026.
Allocation is the amount provided in the ADP 2026-27. Released is the amount released so far this year. Utilized is the amount utilized out of the funds released. Capital and revenue are shown separately and are never added into one percentage.
LTBC means the scheme is likely to be completed by June 2027. All amounts are in Rs million.