ADP No. 899 LTBC
Up gradation of Basic Health Unit to Rural Health Centre at Kharoro Syed, Taluka Umerkot
- ADP No.
- 899
- District(s)
- Umerkot
- Division
- Mirpurkhas
- Facility type
- RHC
- ADP target date
- 30-06-2027
- LTBC
- Yes
- Executing agency
- Works & Services Department (capital); Procurement, Monitoring & Implementation Cell, Health Department (revenue)
Capital as on 30-10-2026 · Revenue as on 23-10-2026. Rs in million.
Up to 30 June 2026
Approved cost214Latest approved cost
Utilized to 30 June 20266027.8% of cost · ADP estimate
Throw-forward155Balance as on 1 July 2026 · equal to allocation for 2026-27
Financial year 2026-27
Allocation155Capital110.817Revenue44.011
Released83Capital38.786Revenue44.011
Utilized16Capital16.413RevenueNil
By component Utilization against funds released
Capital
42.3% of release utilizedAllocation110.817Released38.786Utilized16.413Of allocation14.8%Revenue
0.0% of release utilizedAllocation44.011Released44.011UtilizedNilOf allocation0.0%Released and utilized against allocation, 2026-27
How to read this page
Approved cost is the latest approved cost of the scheme. Utilized to 30 June 2026 is the estimate printed in the ADP. Throw-forward is the balance of the approved cost on 1 July 2026.
Allocation is the amount provided in the ADP 2026-27. Released is the amount released so far this year. Utilized is the amount utilized out of the funds released. Capital and revenue are shown separately and are never added into one percentage.
LTBC means the scheme is likely to be completed by June 2027. All amounts are in Rs million.