ADP No. 911 LTBC
Establishment of BHU at Village Bakoo, UC & Taluka Nangarparkar
- ADP No.
- 911
- District(s)
- Tharparkar
- Division
- Mirpurkhas
- Facility type
- BHU
- ADP target date
- 30-06-2027
- LTBC
- Yes
- Executing agency
- Works & Services Department (capital); Procurement, Monitoring & Implementation Cell, Health Department (revenue)
Capital as on 30-10-2026 · Revenue as on 23-10-2026. Rs in million.
Up to 30 June 2026
Approved cost100Latest approved cost
Utilized to 30 June 20265049.8% of cost · ADP estimate
Throw-forward50Balance as on 1 July 2026 · equal to allocation for 2026-27
Financial year 2026-27
Allocation50Capital37.884Revenue12.480
Released26Capital13.260Revenue12.480
Utilized13Capital12.581RevenueNil
By component Utilization against funds released
Capital
94.9% of release utilizedAllocation37.884Released13.260Utilized12.581Of allocation33.2%Revenue
0.0% of release utilizedAllocation12.480Released12.480UtilizedNilOf allocation0.0%Released and utilized against allocation, 2026-27
How to read this page
Approved cost is the latest approved cost of the scheme. Utilized to 30 June 2026 is the estimate printed in the ADP. Throw-forward is the balance of the approved cost on 1 July 2026.
Allocation is the amount provided in the ADP 2026-27. Released is the amount released so far this year. Utilized is the amount utilized out of the funds released. Capital and revenue are shown separately and are never added into one percentage.
LTBC means the scheme is likely to be completed by June 2027. All amounts are in Rs million.