ADP No. 917  LTBC

Up gradation of Government Dispensary to Basic Health Unit at Village Kasbo, Taluka Nangarparkar

ADP No.
917
District(s)
Tharparkar
Division
Mirpurkhas
Facility type
BHU
ADP target date
30-06-2027
LTBC
Yes
Executing agency
Works & Services Department (capital); Procurement, Monitoring & Implementation Cell, Health Department (revenue)

Capital as on 23-10-2026 · Revenue as on 23-10-2026. Rs in million.

Up to 30 June 2026

Approved cost48Latest approved cost
Utilized to 30 June 2026Nil0.0% of cost · ADP estimate
Throw-forward48Balance as on 1 July 2026 · equal to allocation for 2026-27

Financial year 2026-27

Allocation48Capital38.251Revenue9.523
Released19Capital19.125RevenueNil
UtilizedNilCapitalNilRevenueNil

By component Utilization against funds released

Capital

0.0% of release utilizedAllocation38.251Released19.125UtilizedNilOf allocation0.0%

Revenue

Allocation9.523ReleasedNilUtilizedNil

Released and utilized against allocation, 2026-27

Capital

  • Allocation38.251
  • Released19.125
  • UtilizedNil

Revenue

  • Allocation9.523
  • ReleasedNil
  • UtilizedNil

How to read this page

Approved cost is the latest approved cost of the scheme. Utilized to 30 June 2026 is the estimate printed in the ADP. Throw-forward is the balance of the approved cost on 1 July 2026.

Allocation is the amount provided in the ADP 2026-27. Released is the amount released so far this year. Utilized is the amount utilized out of the funds released. Capital and revenue are shown separately and are never added into one percentage.

LTBC means the scheme is likely to be completed by June 2027. All amounts are in Rs million.