ADP No. 919 LTBC
Up gradation of GD Giryanchho to BHU Giryanchho and Construction of New Government Dispensary at Village (01) Goga Bheel UC Boharirhi (02) Village Samaro Bheel Paro Tahoo Bheel UC Bapuhar and (03) Village Sajan Bheel Warhon UC Morhano
- ADP No.
- 919
- District(s)
- Tharparkar
- Division
- Mirpurkhas
- Facility type
- BHU
- ADP target date
- 30-06-2027
- LTBC
- Yes
- Executing agency
- Works & Services Department (capital); Procurement, Monitoring & Implementation Cell, Health Department (revenue)
Capital as on 23-10-2026 · Revenue as on 23-10-2026. Rs in million.
Up to 30 June 2026
Approved cost75Latest approved cost
Utilized to 30 June 2026Nil0.0% of cost · ADP estimate
Throw-forward75Balance as on 1 July 2026 · equal to allocation for 2026-27
Financial year 2026-27
Allocation75Capital61.007Revenue13.963
Released31Capital30.503RevenueNil
UtilizedNilCapitalNilRevenueNil
By component Utilization against funds released
Capital
0.0% of release utilizedAllocation61.007Released30.503UtilizedNilOf allocation0.0%Revenue
Allocation13.963ReleasedNilUtilizedNilReleased and utilized against allocation, 2026-27
How to read this page
Approved cost is the latest approved cost of the scheme. Utilized to 30 June 2026 is the estimate printed in the ADP. Throw-forward is the balance of the approved cost on 1 July 2026.
Allocation is the amount provided in the ADP 2026-27. Released is the amount released so far this year. Utilized is the amount utilized out of the funds released. Capital and revenue are shown separately and are never added into one percentage.
LTBC means the scheme is likely to be completed by June 2027. All amounts are in Rs million.