Health ADP 2026-27Health Department · Government of SindhScheme dashboard — sign in

ADP No. 919  LTBC

Up gradation of GD Giryanchho to BHU Giryanchho and Construction of New Government Dispensary at Village (01) Goga Bheel UC Boharirhi (02) Village Samaro Bheel Paro Tahoo Bheel UC Bapuhar and (03) Village Sajan Bheel Warhon UC Morhano

ADP No.
919
District(s)
Tharparkar
Division
Mirpurkhas
Facility type
BHU
ADP target date
30-06-2027
LTBC
Yes
Executing agency
Works & Services Department (capital); Procurement, Monitoring & Implementation Cell, Health Department (revenue)

Capital as on 23-10-2026 · Revenue as on 23-10-2026. Rs in million.

Up to 30 June 2026

Approved cost75Latest approved cost
Utilized to 30 June 2026Nil0.0% of cost · ADP estimate
Throw-forward75Balance as on 1 July 2026 · equal to allocation for 2026-27

Financial year 2026-27

Allocation75Capital61.007Revenue13.963
Released31Capital30.503RevenueNil
UtilizedNilCapitalNilRevenueNil

By component Utilization against funds released

Capital

0.0% of release utilizedAllocation61.007Released30.503UtilizedNilOf allocation0.0%

Revenue

Allocation13.963ReleasedNilUtilizedNil

Released and utilized against allocation, 2026-27

Capital

  • Allocation61.007
  • Released30.503
  • UtilizedNil

Revenue

  • Allocation13.963
  • ReleasedNil
  • UtilizedNil

How to read this page

Approved cost is the latest approved cost of the scheme. Utilized to 30 June 2026 is the estimate printed in the ADP. Throw-forward is the balance of the approved cost on 1 July 2026.

Allocation is the amount provided in the ADP 2026-27. Released is the amount released so far this year. Utilized is the amount utilized out of the funds released. Capital and revenue are shown separately and are never added into one percentage.

LTBC means the scheme is likely to be completed by June 2027. All amounts are in Rs million.